Summer 2020 |
---|
Splashlands opens during the town's centenary year. |
.
.
Winter 2019 |
---|
The first part of the splash pad pump and filter system are installed. |
.
.
Autumn 2019 |
---|
A ground-breaking event on Wednesday 30 October marked the start of construction on the new Splashlands facility. Site hoardings are installed enabling works to commence safely |
.
.
Summer 2019 |
---|
Work completes on the toilet block and kiosk. The council's Development Management Commitee votes unanimously in favour of granting planning approval for Splashlands. |
.
.
Spring 2019 |
---|
Work starts on site on the toilet block and a planning application is submitted for the Splashlands project. |
.
.
March 2019 |
---|
The council hosts two public exhibitions to unveil designs for Splashlands. |
.
.
January 2019 |
---|
A planning application is submitted for alterations to the exterior of the existing toilet block. |
.
.
December 2018 |
---|
Cabinet agrees to progress proposals for a new leisure facility at Stanborough Park North, including a nautical themed splash park. |